docs(01): plan phase 1 cleanup & fixes
This commit is contained in:
+7
-5
@@ -1,14 +1,13 @@
|
|||||||
---
|
---
|
||||||
gsd_state_version: 1.0
|
gsd_state_version: 1.0
|
||||||
milestone: v1.0
|
milestone: v1.0
|
||||||
milestone_name: Portfolio Hytale-first
|
milestone_name: milestone
|
||||||
status: planning
|
status: Ready to execute
|
||||||
last_updated: "2026-04-10"
|
last_updated: "2026-04-10T16:56:12.567Z"
|
||||||
last_activity: 2026-04-10 -- Project initialized with research
|
|
||||||
progress:
|
progress:
|
||||||
total_phases: 4
|
total_phases: 4
|
||||||
completed_phases: 0
|
completed_phases: 0
|
||||||
total_plans: 0
|
total_plans: 2
|
||||||
completed_plans: 0
|
completed_plans: 0
|
||||||
percent: 0
|
percent: 0
|
||||||
---
|
---
|
||||||
@@ -16,13 +15,16 @@ progress:
|
|||||||
# Project State
|
# Project State
|
||||||
|
|
||||||
## Project Reference
|
## Project Reference
|
||||||
|
|
||||||
- PROJECT.md: .planning/PROJECT.md
|
- PROJECT.md: .planning/PROJECT.md
|
||||||
- REQUIREMENTS.md: .planning/REQUIREMENTS.md
|
- REQUIREMENTS.md: .planning/REQUIREMENTS.md
|
||||||
- ROADMAP.md: .planning/ROADMAP.md
|
- ROADMAP.md: .planning/ROADMAP.md
|
||||||
|
|
||||||
## Current Focus
|
## Current Focus
|
||||||
|
|
||||||
Phase 1: Cleanup & Fixes — ready for planning
|
Phase 1: Cleanup & Fixes — ready for planning
|
||||||
|
|
||||||
## Session Notes
|
## Session Notes
|
||||||
|
|
||||||
- Project initialized 2026-04-10 with codebase mapping + 4-agent research
|
- Project initialized 2026-04-10 with codebase mapping + 4-agent research
|
||||||
- Brownfield: Nuxt 4 SSR portfolio already functional, needs content pivot to Hytale + SEO fixes
|
- Brownfield: Nuxt 4 SSR portfolio already functional, needs content pivot to Hytale + SEO fixes
|
||||||
|
|||||||